Question: Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 1 3 3 2 2 4 2
Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 1 3 3 2 2 4 2 5 5 3, 4 4 The required project completion time is 15. Assume that "Activity 1" actually finished at 3 weeks, and "Activity 2" actually finished at 7 weeks. Given the actual project progress, what is the LF (lastest time) of "Activity 4