Question: Given below is the baseline planned value ( PV ) budget information for a project. Provide a status report as of the end of Period

Given below is the baseline planned value (PV) budget information for a project. Provide a status report as of the end of Period 4.
Formula:
EV =% complete*PV
CV = EV - AC
CPI = EV / AC
SV = EV - PV
SPI = EV / PV
PCIB = EV/BAC
ETC =[(BAC - EV)/ CPI]
EACf = AC +[(BAC - EV)/ CPI]