Question: Given below is the baseline planned value (PV) budget information for a project. Provide a status report as of the end of Period 4. Formula:

Given below is the baseline planned value (PV) budget information for a project. Provide a status report as of the end of Period 4.

Formula:

EV = % complete*PV

CV = EV - AC

CPI = EV / AC

SV = EV - PV

SPI = EV / PV

PCIB = EV/BAC

ETC = [(BAC - EV) / CPI]

EACf = AC + [(BAC - EV) / CPI]

VAC = BAC-EACf

Given below is the baseline planned value (PV)

Given below is the baseline planned value (PV)

End of Period 4

Task

Actual %

EV

AC

PV

CV

SV

Complete

$

$

$

$

$

A

Finished

300

400

B

50%

1000

800

C

30%

500

600

D

0%

0

E

0%

Cumulative Totals

2100

What percentage of the entire project has been completed as of the end of period 4? (hint: use PCIB)

16.2%

61.2%

85.7%

28.3%

14.2%

LEGEND ES ID EF SL SL 2 B8 8 D 12 0 0 LS DUR LF O 0 0 2 68 84 12 0 A 2 12 F 15 0 0 0 0 22 2 12 3 15 2 C 7 7 E 10 2 2 2 2 4 59 9 3 12 Project baseline (PV) (in $) Task DUR ES LF SL 10 11 12 13 14 15 Budget (PV) o 1 2 3 4 5 6 7 8 9 400 200 200 2400 200 600 200 600 200 600 2 0 2 0 B 6 2 0 5 2 9 2 1500 200 400 500 100 300 D 4 8 12 0 E 3 7 12 1600 400 400 400 400 2 900 300 400 200 0 200 100 300 Period PV total 200 200 400 1000 700 700 500 900 800 600 400 400 200 100 300 F 3 12 15 600 Cumulative PV total 200 400 800 1800 2500 3200 3700 4600 5400 6000 6400 6800 7000 7100 7400

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!