Question: Given is a CPM proiect network diaaram as shown below. table [ [ Activity , Start,A , B , C , D , E

Given is a CPM proiect network diaaram as shown below.
\table[[Activity,Start,A,B,C,D,E,F,G,H,End],[day,0,3,8,6,7,3,4,5,8,0]]
a) The Project Completion time = Blank 1? days.
b) The Earliest Start time, ES, of Activity G= Blank 2 days.
c) The Latest Finish time, LF, of Activity C= Blank 3 days.
d) The critical activities are = Blank 4(ex. Fill in the answer as: ABCD)?
 Given is a CPM proiect network diaaram as shown below. \table[[Activity,Start,A,B,C,D,E,F,G,H,End],[day,0,3,8,6,7,3,4,5,8,0]]