Question: Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day 6 B

Given is a CPM project network diagram as shown
Given is a CPM project network diagram as shown below. A F Start E H End B D G Start H Activity day 6 B 3 8 D 7 E 4 F 9 G 4 End 0 0 6 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G - days. c) The Latest Finish time, LF, of Acitivity - dayy d) The critical activities are (ex. Fill in answer as: ABCD)