Question: Given is a CPM project network diagram as shown below. a) The Project Completion time =Blank1 days. b) The Earliest Start time, ES, of Activity

Given is a CPM project network diagram as shown below. a) The Project Completion time =Blank1 days. b) The Earliest Start time, ES, of Activity G - Blank 2 days. c) The Latest Finish time, LF, of Activity C = Blank 3 days. d) The critical activities are = Blank 4( ex. Fill in the answer as: ABCD) Blank 1 Add your answer Blank 2 Add your answer Blank 3 Add your answer Blank 4 Add your