Question: Given is a CPM project network diagram as shown below. a) The Project Completion time =Blank1 days. b) The Earliest Start time, ES, of Activity

Given is a CPM project network diagram as shown

Given is a CPM project network diagram as shown below. a) The Project Completion time =Blank1 days. b) The Earliest Start time, ES, of Activity G=Blank2 days. c) The Latest Finish time, LF, of Activity C=Blank3 days. d) The critical activities are =Blank4 (ex. Fill in the answer as: ABCD)