Question: Given is a CPM project network diagram as shown below A c F Start E End H B B D G and Activity Start days

Given is a CPM project network diagram as shown
Given is a CPM project network diagram as shown below A c F Start E End H B B D G and Activity Start days 2 a) The Project Completion time days.) by The Earliest Start time, ES, of Activity - days c) The Latest Finish time, LF, of Activity - days di The critical activities are (ex. Fill in answer as ABCD)