Question: QUESTION 1 Given is a CPM project network diagram as shown below. A F F Start E H End B D G Activity day Start

QUESTION 1 Given is a CPM project network diagram

QUESTION 1 Given is a CPM project network diagram as shown below. A F F Start E H End B D G Activity day Start 0 5 B 8 3 D 5 E 6 F 8 G 3 H 4 End 0 a) The Project Completion time = days. b) The Earliest Start time. ES. of Activity G= days. c) The Latest Finish time. LF, of Acitivity C = days. d) The critical activities are = (ex. Fill in answer as: ABCD)