Question: Given is a PERT project network diagram as shown below F Start E H End B D G Activity Time Start 0 3.56 B 2.63

Given is a PERT project network diagram as shown
Given is a PERT project network diagram as shown below F Start E H End B D G Activity Time Start 0 3.56 B 2.63 7.21 D 3.96 E 1.82 F 1.63 G 6.42 H 3.52 End 0 a) The Project Completion time (in 2 decimal places) b) The Earliest Start time, ES, of Activity G = (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C= I (in 2 decimal places) For Blank (ex. type in critical activities as ABCD no comma, no space) d) The critical activities are