Question: Given is a PERT project network diagram as shown below. Activity Start A B C D E F G H End Time 0 1.52 2.36
Given is a PERT project network diagram as shown below.
| Activity | Start | A | B | C | D | E | F | G | H | End |
| Time | 0 | 1.52 | 2.36 | 7.02 | 3.69 | 1.28 | 4.36 | 6.24 | 3.25 | 0 |
a) The Project Completion time = __________ (in 2 decimal places) b) The Earliest Start time, ES, of Activity G = ___________ (in 2 decimal places) c) The Latest Finish time, LF, of Acitivity C = ___________ (in 2 decimal places) d) The critical activities are = ____________ (ex. type in critical activities as ABCD, no comma, no space)