Question: Given is a Project with network diagram and activity times as shown below. E H Start Activity Time wks) 11 B 2 6 D 12

Given is a Project with network diagram and
Given is a Project with network diagram and
Given is a Project with network diagram and activity times as shown below. E H Start Activity Time wks) 11 B 2 6 D 12 E 9 F 16 G 5 NI -100 lu Activity Time (wks) 11 N00 6 D 12 E 9 F 16 10 L IN 1 8 Chic a) The Earliest Start (ES) time of Activity I - weeks b) The Latest Start (LS) time of Activity B = weeks c) The Slack time of Activity C - weeks d) The Earliest Finish (EF) time of Activity H = weeks e) The Latest Finish (LF) time of Activity B weeks f) The Project Completion time = weeks