Question: Given is a Project with network diagram and activity times as shown below. E B H Start F - J Activity Time (wks) A 7

Given is a Project with network diagram and
Given is a Project with network diagram and
Given is a Project with network diagram and activity times as shown below. E B H Start F - J Activity Time (wks) A 7 B 8 12 D 8 E 8 F 14 G 15 H 4 7 5 F Activity Time (wks) 7 B 8 C 12 D 8 E 8 F 14 H 4 J 5 15 7 a) The Earliest Start (ES) time of Activity I = weeks b) The Latest Start (LS) time of Activity B = weeks c) The Slack time of Activity C= weeks d) The Earliest Finish (EF) time of Activity H = weeks e) The Latest Finish (LF) time of Activity B = weeks f) The Project Completion time = weeks