Question: Given is a Project with network diagram and activity times as H Sant Activity Time (wks) 3 H 14 D 17 IT G 17 IL

Given is a Project with network diagram and
Given is a Project with network diagram and activity times as H Sant Activity Time (wks) 3 H 14 D 17 IT G 17 IL 17 16 13 16 15 a) The Earliest Start (ES) time of Activity 1 - 17 weeks b) The Latest Start (LS) time of Activity B = 3 weeks c) The Slack time of Activity C - weeks d) The Earliest Finish (EF) time of Activity H - weeks e) The Latest Finish (LF) time of Activity B = weeks 1) The Project Completion time = weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!