Question: Given is a Project with network diagram and activity times as shown below. f) The Project Completion time = Blank 6 weeks There should be
Given is a Project with network diagram and activity times as shown below.
f) The Project Completion time = Blank 6 weeks
There should be 6 answers!!
a) The Earliest Start (ES) time of Activity I = Blank 1 weeks b) The Latest Start (LS) time of Activity B = Blank 2 weeks c) The Slack time of Activity C = Blank 3 weeks d) The Earliest Finish (EF) time of Activity H=Blank4 weeks e) The Latest Finish (LF) time of Activity B =Blank5 weeksStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts