Question: Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI. Consider

Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI.

Consider it is currently at the end of Month 2. This implies that task 6 was planned to be completed but was not started. Be sure to show all of your work.

Planned Schedule and Budget

Actual Cost

Task

Month 1

Month 2

Month 3

1

$4,000

$6,000

2

$1,000

$4,000

3

$3,000

$4,000

4

$5,000

$1,000

5

$5,000

$4,000

6

$3,000

7

$1,000

8

$2,000

9

$4,000

Total

$8,000

$13,000

$7,000

$19,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!