Question: Given the BOM information below, find the planned orders release of item A in week 2. A B rag 2) Part A Lot size 25

Given the BOM information below, find the planned

Given the BOM information below, find the planned orders release of item A in week 2. A B rag 2) Part A Lot size 25 Lead time (Week) 1 Safety Stock 0 Part B 50 2 0 Part C Lot for Lot 1 15 A N 6 1 15 3 21 4 19 5 20 23 24 20 Gross requirements Scheduled receipts Projected on-hand Projected on-hand-sS Net requirements Planned order receipts Planned orders release 18 18 0 25 O 50