Question: Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are




Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost?





Exercise 4 (a) ACT. NORMAL NORMAL MAXIMU CRASH TIME COST M CRASH COST TIME (per week) 5 50 1 20 60 2 60 4X 70 0 0 50 10 -IOnMOOD 100 60 UNUIN 90 100 HOHHWA 50 30 2X 60 40 W 200 200 $730\fC F Project Duration 12 CP = A D G Activities changed B E H Total Direct CostC F Project Duration 14 A CP = D G Activities changed B E H Total Direct Cost C F Project Duration 13 A CP = D G Activities changed B E H Total Direct Cost(c) C F Project Duration 11 A D G Activities changed B E H $1150
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
