Question: Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are

 Given the data and information that follow, compute the total directcost for each project duration. If the indirect costs for each projectduration are $90 (15 time units), $70 (14), $50 (13), $40 (12),and $30 (11), compute the total project cost for each duration. What

Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is this cost?

is the optimum cost-time schedule for the project? What is this cost?Exercise 4 (a) ACT. NORMAL NORMAL MAXIMU CRASH TIME COST M CRASHCOST TIME (per week) 5 50 1 20 60 2 60 4X70 0 0 50 10 -IOnMOOD 100 60 UNUIN 90 100 HOHHWA50 30 2X 60 40 W 200 200 $730\fC F Project Duration

Exercise 4 (a) ACT. NORMAL NORMAL MAXIMU CRASH TIME COST M CRASH COST TIME (per week) 5 50 1 20 60 2 60 4X 70 0 0 50 10 -IOnMOOD 100 60 UNUIN 90 100 HOHHWA 50 30 2X 60 40 W 200 200 $730\fC F Project Duration 12 CP = A D G Activities changed B E H Total Direct CostC F Project Duration 14 A CP = D G Activities changed B E H Total Direct Cost C F Project Duration 13 A CP = D G Activities changed B E H Total Direct Cost(c) C F Project Duration 11 A D G Activities changed B E H $1150

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!