Question: Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are

Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50(13),$40(12), and $30 (11), compute the total project cost for ench duration. What is the optimum cost-time schedule for the project? What is this cost
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
