Question: Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are

Given the data and information that follow, compute the total direct cost for each project duration.
If the indirect costs for each project duration are $90(15-time units), $70(14), $50(13), $40(12), and $30(11), compute the total project cost for each duration. What is the optimum cost-time schedule for the project? What is the total cost?
Provide your answers demonstrating and explaining your calculations, schedules, and your assessment of your conclusion.