Question: Given the data in the table below, draw both the arrow network and the node network, and Determine the critical path/s. Calculate and indicate the
Given the data in the table below, draw both the arrow network and the node network, and Determine the critical path/s. Calculate and indicate the Early Start, Early Finish schedule, Late Start, Late Finish schedule, Free Float and Total Float of each activity.

Activity Duration A 8 B | C Predecessor Duration Activity Predecessor 3 1 G H A 5 J I A 6 K H A 5 L H B, C 7 M I D 10 N I, K E 9 O L F 10 P M, N, O 7 12 10 D E 9 8 | I | G F G . 5 | | 0 TM 4
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
