Question: Given the data in the table below, draw both the arrow network and the node network, and Determine the critical path/s. Calculate and indicate the

Given the data in the table below, draw both the arrow network and the node network, and Determine the critical path/s. Calculate and indicate the Early Start, Early Finish schedule, Late Start, Late Finish schedule, Free Float and Total Float of each activity.

Given the data in the table below, draw both the

Activity Duration A 8 B | C Predecessor Duration Activity Predecessor 3 1 G H A 5 J I A 6 K H A 5 L H B, C 7 M I D 10 N I, K E 9 O L F 10 P M, N, O 7 12 10 D E 9 8 | I | G F G . 5 | | 0 TM 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!