Question: Given the follow production line: Task a ( 2 min ) - - - - - - - - - - - - > Task

Given the follow production line:
Task a (2 min)------------>Task b (4 min)------------>Task c (3 min)------------>Task d (2 min)
What is the cycle time?
Group of answer choices
3 minutes
11 minutes
4 minutes
2 minutes