Question: Given the following activity network: A2 A1 AS Activity A1 takes 5 weeks, A2 takes 6 weeks, and A3 takes 2 weeks. What is the

Given the following activity network: A2 A1 AS
Given the following activity network: A2 A1 AS Activity A1 takes 5 weeks, A2 takes 6 weeks, and A3 takes 2 weeks. What is the latest completion time of A3? 13 weeks 7 weeks 11 weeks 8 weeks