Question: Given the following activity network (activity time in week is on top of each activity). What is the earliest start time of activity D? A

Given the following activity network (activity time in week is on top of each activity). What is the earliest start time of activity D? A 2 weeks B, 4 weeks C. 7 weeks D. 11 weeks Given the following activity network (activity time in week is on top of each activity). Finish What is the earliest completion time of C? A. 7 weeks B, 11 weeks C, 2 weeks D. 5 weeks