Question: Given the following data, calculate EAC based on Cumulative Cost performance index as the performance factor. Round to the nearest dollar. BAC=1000; BCWS=500; BCWP=400; AWCP=500
Given the following data, calculate EAC based on Cumulative Cost performance index as the performance factor. Round to the nearest dollar. BAC=1000; BCWS=500; BCWP=400; AWCP=500
1000
600
900
1425