Question: Given the following data, fill the blanks in the table. Note that a, m, and b are in days. Answer all the questions below. Show

Given the following data, fill the blanks in the table. Note that a, m, and b are in days. Answer all the questions below. Show your formulas and/or details where appropriate.

Task

Predecessor

a

m

b

ET

Slack

Variance

A

-

5

5

5

B

A

7

9

17

C

B,D

5

7

9

D

-

10

10

10

E

C

2

3

4

F

B,D

4

6

8

G

F

4

6

14

H

E

8

9

10

I

E

1

3

5

J

G,H,I

4

6

8

Draw the CPM diagram here:

Critical Path:

Expected Project Completion Time:

Standard Deviation of Project Completion Time:

Probability of completing the project in 36 days:

Find the time where the probability of project being delayed is 0.02 or less?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Step 1 Construct the CPM Critical Path Method Network Diagram Lets start by drawing the CPM network diagram based on the given data Tasks and their du... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!