Question: Given the following data, fill the blanks in the table. Note that a, m, and b are in days. Answer all the questions below. Show
Given the following data, fill the blanks in the table. Note that a, m, and b are in days. Answer all the questions below. Show your formulas and/or details where appropriate.
Task | Predecessor | a | m | b | ET | Slack | Variance |
A | - | 5 | 5 | 5 | |||
B | A | 7 | 9 | 17 | |||
C | B,D | 5 | 7 | 9 | |||
D | - | 10 | 10 | 10 | |||
E | C | 2 | 3 | 4 | |||
F | B,D | 4 | 6 | 8 | |||
G | F | 4 | 6 | 14 | |||
H | E | 8 | 9 | 10 | |||
I | E | 1 | 3 | 5 | |||
J | G,H,I | 4 | 6 | 8 |
Draw the CPM diagram here:
Critical Path:
Expected Project Completion Time:
Standard Deviation of Project Completion Time:
Probability of completing the project in 36 days:
Find the time where the probability of project being delayed is 0.02 or less?
Step by Step Solution
There are 3 Steps involved in it
Step 1 Construct the CPM Critical Path Method Network Diagram Lets start by drawing the CPM network diagram based on the given data Tasks and their du... View full answer