Question: Given the following data for a project: Time (days) Activity Predecessors Normal Crash Cost to crash/day A - 3 2 $600 B - 2 1

Given the following data for a project:

Time (days)

Activity Predecessors Normal Crash Cost to crash/day

A - 3 2 $600

B - 2 1 700

C A 5 3 400

D B 5 3 400

E C , D 6 4 500

F C , D 2 1 400

G F 2 1 500

  1. Draw the PERT network.
  2. This project must be completed by 11 days. What is the minimum incremental cost of doing this?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!