Question: Given the following data for a project: Time (days) Activity Predecessors Normal Crash Cost to crash/day A - 3 2 $600 B - 2 1
Given the following data for a project:
Time (days)
Activity Predecessors Normal Crash Cost to crash/day
A - 3 2 $600
B - 2 1 700
C A 5 3 400
D B 5 3 400
E C , D 6 4 500
F C , D 2 1 400
G F 2 1 500
- Draw the PERT network.
- This project must be completed by 11 days. What is the minimum incremental cost of doing this?