Question: The following table provides the information necessary to construct a project network and project crash data. Construct the project network using the AON method, and
The following table provides the information necessary to construct a project network and project crash data.
Construct the project network using the AON method, and crash the network the maximum amount possible.
What is the normal cost to complete the project? What is the additional cost to crash the project? marks
Activity Predecessors Normal Crash Normal Crash
A $ $
B
C A
D A
E B
F B
G C
H DE
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
