Question: Given the following information belows: Activity Duration Predecessors A 2 weeks Start B 3 weeks Start C 5 weeks Start D 7 weeks A E

Given the following information belows:
Activity Duration Predecessors
A 2 weeks Start
B 3 weeks Start
C 5 weeks Start
D 7 weeks A
E 3 weeks B
F 2 weeks C
G4 weeks F
H 1 week A
18 Weeks D,E,G
1.5 weeks F
K.2 weeks D,E,G,H
A. Determine the Critical Path and Project Duration.
B. What is the slack time (float) for activities A, B, G. and I?