Question: Given the following information below: Activity Duration Predecessors A 3 weeks Start B 3 weeks Start C 5 weeks Start D 7 weeks A E

Given the following information below:

Activity Duration Predecessors

A 3 weeks Start

B 3 weeks Start

C 5 weeks Start

D 7 weeks A

E 3 weeks B

F 2 weeks C

G 4 weeks F

H 1 week A

I 8 weeks D,E,G

J 5 weeks F

K 2 weeks D,E,G,H

A. Determine the Critical Path and Project Duration.

B. What is the slack time (float) for activities A, B, G, and J?