Question: Given the following information below: Activity Duration Predecessors A 3 weeks Start B 3 weeks Start C 5 weeks Start D 7 weeks A E
Given the following information below:
Activity Duration Predecessors
A 3 weeks Start
B 3 weeks Start
C 5 weeks Start
D 7 weeks A
E 3 weeks B
F 2 weeks C
G 4 weeks F
H 1 week A
I 8 weeks D,E,G
J 5 weeks F
K 2 weeks D,E,G,H
A. Determine the Critical Path and Project Duration.
B. What is the slack time (float) for activities A, B, G, and J?