Question: Using the provided data values for minimum expected activity durations and maximum expected activity durations, use Excel to provide a PERT analysis of the project
Using the provided data values for minimum expected activity durations and maximum expected activity durations, use Excel to provide a PERT analysis of the project given in question
Your spreadsheet should indicate the early start schedule, late start schedule, and slack.
Activity
Duration
Predecessors
A
3 weeks
B
15 weeks
A
C
5 weeks
B
D
3 weeks
C
E
6 weeks
B
F
4 weeks
E
G
2 weeks
D, F
Include all calculations demonstrated in Figure 13.12.
Activity
Minimum Duration
Maximum Duration
A
2
4
B
12
18
C
3
7
D
2
4
E
4
8
F
3
5
G
1
3