Question: Using the provided data values for minimum expected activity durations and maximum expected activity durations, use Excel to provide a PERT analysis of the project

Using the provided data values for minimum expected activity durations and maximum expected activity durations, use Excel to provide a PERT analysis of the project given in question

Your spreadsheet should indicate the early start schedule, late start schedule, and slack.

Activity

Duration

Predecessors

A

3 weeks

B

15 weeks

A

C

5 weeks

B

D

3 weeks

C

E

6 weeks

B

F

4 weeks

E

G

2 weeks

D, F

Include all calculations demonstrated in Figure 13.12.

Activity

Minimum Duration

Maximum Duration

A

2

4

B

12

18

C

3

7

D

2

4

E

4

8

F

3

5

G

1

3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!