Question: Given the following information, develop a material requirements plan for end item A and its components. 95 and 40 units of A are needed at

Given the following information, develop a

Given the following information, develop a material requirements plan for end item A and its components. 95 and 40 units of A are needed at the beginning of week 6 and 8, respectively. On-Order Item A On-Hand 25 10 09 20 (wk 2) MUAL Lead Time 1 wk 1 wk 2 wks 1 wk 2 wks Order Size lot-for-lot lot-for-lot lot-for-lot 100 200 100 F A B(3) C(2) - F D F(2) The planned-order release for product B is: Week 4: 255 0 Week 4: 195, Week 6: 120 Week 4: 180, Week 6: 120 O O Week 4: 285, Week 6: 120 o Week 5: 285, Week 7: 130