Question: Given the following information for a one - year project, PV : $ 4 7 , 0 0 0 , EV : $ 4 0

Given the following information for a one-year project, PV : $47,000, EV : $40,000, AC
:$49,000 and BAC : $240,000
(a) What is the cost variance, schedule variance, cost performance index(CPl) and schedule
performance index(SPl) for the project?
(b) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or
over budget?