Question: Given the following information for a one - year project, answer the following questions. Assume you have actual and earned value data at the end
Given the following information for a oneyear project, answer the following questions. Assume you have actual and earned value data at the end of the second month. Recall that BCWS is the planned value, BCWP is the earned value, ACWP is the actual cost, and BAC is the budget at completion.
$
$
ACWP$
BAC$
What is the
cost variance
schedule variance,
cost performance index
schedule performance index
How is the project progressing
Is it a head of schedule or behind schedule
Is it under budget or over budget
Using the above information we can calculate Estimate At Completion meaning if we continue WITHOUT making adjustments to the project how much will the project cost at completion and how long will it take.
Use the CPI to calculate the estimate at completion EAC for this project.
Use the SPI to estimate the how long it will take to finish this project. Planned TimeSPI
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
