Question: Given the following information for a one-year project, answer the following questions. Note: Assume you have actual and earned value data at the end of

  1. Given the following information for a one-year project, answer the following questions.

Note: Assume you have actual and earned value data at the end of the second month.

PV= $23,000

EV= $20,000

AC= $25,000

BAC= $120,000

  1. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
  2. How is the project progressing? Is it ahead of schedule or behind schedule? Is it over or under budget?
  3. Use the CPI to calculate the estimate at completion (EAC) for this project.
  4. Use the SPI to estimate how long it will take to finish this project.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!