Question: Given the following information for a one-year project, answer the following questions. Note: Assume you have actual and earned value data at the end of
- Given the following information for a one-year project, answer the following questions.
Note: Assume you have actual and earned value data at the end of the second month.
PV= $23,000
EV= $20,000
AC= $25,000
BAC= $120,000
- What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
- How is the project progressing? Is it ahead of schedule or behind schedule? Is it over or under budget?
- Use the CPI to calculate the estimate at completion (EAC) for this project.
- Use the SPI to estimate how long it will take to finish this project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
