Question: Given the following information for a project, determine the critical path. Activity Immediate Processor Activity Time (days) A - 6 B - 8 C A,B
Given the following information for a project, determine the critical path.
| Activity | Immediate Processor | Activity Time (days) |
| A | - | 6 |
| B | - | 8 |
| C | A,B | 5 |
| D | B | 4 |
| E | C | 7 |
| F | C,D | 3 |
| G | D | 6 |
| H | E,F,G | 5 |
| a. | A-C-E-H | |
| b. | B-C-E-H | |
| c. | B-D-F-H | |
| d. | B-D-G-H | |
| e. | B-C-F-H |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts