Question: Multiple Choice - I will Thumbs up the right answer, thanks QUESTION 5 Given the following information, please answer question 5 to question 8 Activity

Multiple Choice - I will Thumbs up the right answer, thanks

Multiple Choice - I will Thumbs up the right

QUESTION 5 Given the following information, please answer question 5 to question 8 Activity Immediate Predecessors Completion Time (Weeks) N/A Q5. What are the latest start and the latest finish of the activity E? 2.6.11 b. 11.10 6.8.13 d. 18,21 QUESTION 6 What is the total project completion time? QUESTION 7 If activity B was delayed 3 weeks, what is the new total project completion time? OOOO