Question: Given the following information regarding a project: Activity Duration Predecessors a 4 None b 5 None 0 5 a d 6 a e 5 b,c

Given the following information regarding a project: Activity Duration Predecessors a 4 None b 5 None 0 5 a d 6 a e 5 b,c f 4 d g 5 e Which of the following is NOT a path in the network