Question: Given the following information regarding a project: Activity Duration Predecessors a 4 none b 5 none c 5 a d 6 a e 5 b
Given the following information regarding a project:
Activity Duration Predecessors
a none
b none
c a
d a
e bc
f d
g e
Which of the following is NOT a path in the network?
adf
aceg
beg
bfg Correct
What is the critical path?
adf Wrong
aceg
beg
bfg
How long will it take to complete the project?
Wrong
What is the LS for activity a
Correct
What is the LF for activity f
Wrong
What is the EF for activity g
Wrong