Question: Given the following information regarding a project: Activity Duration Predecessors a 4 none b 5 none c 5 a d 6 a e 5 b

Given the following information regarding a project:
Activity Duration Predecessors
a 4 none
b 5 none
c 5 a
d 6 a
e 5 b,c
f 4 d
g 5 e
1. Which of the following is NOT a path in the network?
a-d-f
a-c-e-g
b-e-g
b-f-g (Correct)
2. What is the critical path?
a-d-f (Wrong)
a-c-e-g
b-e-g
b-f-g
3. How long will it take to complete the project?
4(Wrong)
9
10
15
19
4. What is the LS for activity a?
0(Correct)
1
3
4
5
5. What is the LF for activity f?
10(Wrong)
14
15
19
6. What is the EF for activity g?
10(Wrong)
14
15
19
20

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!