Question: Given the following information regarding a project concerning an initial public offering (IPO),LO1 a. Draw the network. b. What is the critical path? c. When
Given the following information regarding a project concerning an initial public offering (IPO),LO1

a. Draw the network.
b. What is the critical path?
c. When will the offering be available (completion of the project)?
d. What is the effect on the project if activity e (approvals)
takes an extra week? Two extra weeks? Three extra weeks?
Activity a: Check feasibility TE Preceding (weeks) Activities 3 none b: Determine funding 1 none c: Find possible banks 3 a d: Select two possibles 4 a e: Interview two banks 4 b f: Analyze funding costs 5 b g: What chance of success? 2 c, e h: Sign contract 3 f