Question: Given the following information regarding a project concerning an initial public offering (IPO),LO1 a. Draw the network. b. What is the critical path? c. When

Given the following information regarding a project concerning an initial public offering (IPO),LO1

Activity a: Check feasibility TE Preceding (weeks) Activities 3 none b: Determine

a. Draw the network.

b. What is the critical path?

c. When will the offering be available (completion of the project)?

d. What is the effect on the project if activity e (approvals)
takes an extra week? Two extra weeks? Three extra weeks?

Activity a: Check feasibility TE Preceding (weeks) Activities 3 none b: Determine funding 1 none c: Find possible banks 3 a d: Select two possibles 4 a e: Interview two banks 4 b f: Analyze funding costs 5 b g: What chance of success? 2 c, e h: Sign contract 3 f

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Project Management Questions!