Question: Given the following network, (a) What is the critical path? (b) How long will it take to complete this project? (c) Can activity B be
Given the following network,

(a) What is the critical path?
(b) How long will it take to complete this project?
(c) Can activity B be delayed without delaying the
completion of the project? If so, how many days?
D7 A8 G5 Start C3 E E6 End B10 F7Step by Step Solution