Question: Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITY E. Activity Duration Predecessor ESEF A 3 - 0

Given the following partially completed Project

Given the following partially completed Project Activity Description and Network Diagram, calculate the SLACK for ACTIVITY E. Activity Duration Predecessor ESEF A 3 - 0 3 8 3 11 9 | 3 12 B 11 19 B, C 12 15 D, E LE 517 LSLF SLACK 0 3 0 3 11 0 7 16 4 11 19 0 A woo 2 311 1119 B, 8 D, 8 F, 5 3 19 3 STARTA, 3 FINISH 12 1215 15 C, 9 E, 3 G2 C3 v OOOOOO w