Question: Given the following PERT data for a given project: Duration time, weeks Activity Most Likely Immediate Optimistic (o) Pessimistic (p) predecessors (m) A 1. 2

Given the following PERT data for a given

Given the following PERT data for a given project: Duration time, weeks Activity Most Likely Immediate Optimistic (o) Pessimistic (p) predecessors (m) A 1. 2 3 B 2. 3 4 4 5 6 A D 8 9 10 B E 2 5 8 C D LL 4 5 6 B G 1 2 3 E 1. Calculate the average duration time and the standard deviation per activity? (4 pts) 2. Find the critical path(s) for this project? (4 pts)