Question: Given the following PERT data for a given project: Duration time, weeks Immediate Most Activity optimistic Likely Pessimistic predecessors (0) (p) (m) A 1 2

Given the following PERT data for a given
Given the following PERT data for a given project: Duration time, weeks Immediate Most Activity optimistic Likely Pessimistic predecessors (0) (p) (m) A 1 2 3 3 B 2 3 4 4 5 6 A D D 8 9 10 m 2 5 8 C D TI 4 5 6 B G 1 2 3 E (4 1. Calculate the average duration time and the standard deviation per activity? pts) 2. Find the critical path(s) for this project? (4 pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!