Question: Given the following PERT data for a given project: Duration time, weeks Immediate Most ActivityOptimistic Likely Pessimistic predecessors (0) (p) (m) A 1 2 3

Given the following PERT data for a given
Given the following PERT data for a given project: Duration time, weeks Immediate Most ActivityOptimistic Likely Pessimistic predecessors (0) (p) (m) A 1 2 3 B 2 3 4 4 6 A 0 0 8 LOL 10 B E 2 8 CD F 4 5 6 B G 1 2 3 E 1. Calculate the average duration time and the standard deviation per activity? (4 pts) 2. Find the critical path(s) for this project? (4 pts)