Question: Given the following Project Activity Description and Network Diagram, select the Critical Path. A. A-D-E B. A-B-D-E-G C. A-C-D-E-G D. A-B-D-F-G E. A-B-E-G F. A-C-F-G
Given the following Project Activity Description and Network Diagram, select the Critical Path.
| A. | A-D-E | |
| B. | A-B-D-E-G | |
| C. | A-C-D-E-G | |
| D. | A-B-D-F-G | |
| E. | A-B-E-G | |
| F. | A-C-F-G | |
| G. | A-C-D-F-G |