Question: Given the following Project Activity Description and Network Diagram, select the Critical Path Given the following project Activity Description and Network Diagram. select the Critical

Given the following project Activity Description and Network Diagram. select the Critical

Given the following Project Activity Description and Network Diagram, select the Critical Path

Given the following project Activity Description and Network Diagram. select the Critical Path. Activity Duration Predecessor ES 12 17 11 4 4 21 26 26 37 EF 16 21 26 37 35 40 21 26 28 37 LF SLACK 21 21 26 37 37 40 STAR A, 4 FINISH c, 17