Question: Given the following project: Activity Predecessor Normal Time (day) Normal Cost ($) Crash Time (day) Crash Cost ($) A - 10 5000 10 5000 B

Given the following project:

Activity

Predecessor

Normal Time (day)

Normal Cost

($)

Crash Time (day)

Crash Cost

($)

A

-

10

5000

10

5000

B

-

12

1200

11

1300

C

A,B

11

3600

9

4800

D

C

5

300

4

600

E

C

8

1000

6

2000

F

C

9

2400

7

5400

G

D,E,F

8

700

7

1000

(a) Draw the network and find

  • the critical path
  • duration of the project,
  • total cost of project using normal times.