Question: Given the following project activity table: Activity Duration Dependency A 8 B 6 A C 4 A D 2 A E 9 B F 3

Given the following project activity table:
Activity Duration Dependency
A 8
B 6 A
C 4 A
D 2 A
E 9 B
F 3 B
G 6 C
H 2 E,F
I 4 F,G
J 1 D,H,I
1) What is the critical path? (Enter the capital letters without spaces or punctuation)
2) What is the length of the project? (Enter no decimal places)
3) What is the slack of activity D?(Enter no decimal places)
4) What is the Late Start of activity F?(Enter no decimal places)
Given the following additional duration data for this project:
Activity Best Case Most Likely Worst Case
A 588
B 369
C 345
D 224
E 5910
F 235
G 469
H 124
I 245
J 113
5) What is the expected duration of activity F?(enter 2 decimal places)
6) What is the standard deviation of activity C?(enter 2 decimal places - if it is less than one, enter the zero and the decimal point)
7) What is the standard deviation of the project? (enter 2 decimal places - if it is less than one, enter the zero and the decimal point)
8) Assuming the expected duration of the project is 23.7 and given the following z table, what is the probability the project will be finished by the original most likely time? (enter it as a decimal - with 2 decimal places - enter the zero and the decimal point)
z value P(Z<=z) Z value P(Z<=z)
-3.00.0010.00.500
-2.50.0060.50.692
-2.00.0231.00.841
-1.50.0671.50.933
-1.00.1592.00.977
-0.50.3092.50.992
3.00.999

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!