Question: Given the following project activity table: Activity Duration Dependency H 5 I 6 H J 4 H K 2 H L 6 I M 3
Given the following project activity table:
Activity Duration Dependency
H
I H
J H
K H
L I
M I
N JK
LM
P MN
Q OP
What is the critical path? Enter the capital letters without spaces or punctuation
What is the length of the project? Enter no decimal places
What is the slack of activity LEnter no decimal places
What is the Late Start of activity MEnter no decimal places
Given the following additional duration data for this project: